Project timeline
01 September 2025 → 31 October 2026
Canning Street Upgrade Project Timeline
Phase 1 – Inform community on design
September 2025
Phase 2 – Inform community on construction schedule
October 2025
Construction begins
October 2025
Underground works - Cambridge Street end
October 2025- December 2025
Christmas break
24 December 2025 - 5 January 2026
Underground works - Albert Street
January 2026 - March 2026
Road reconstruction and footpaths
February 2026 - July 2026
Finishing touches - line-marking, signage, tree planting
July 2026 - October 2026
Expected Project Completion
October 2026
*These dates are subject to weather and ground conditions.