01 September 2025 → 31 October 2026

Canning Street Upgrade Project Timeline

Phase 1 – Inform community on design 

September 2025

Phase 2 – Inform community on construction schedule 

October 2025

Construction begins 

October 2025

Underground works - Cambridge Street end 

October 2025- December 2025

Christmas break 

24 December 2025 - 5 January 2026

Underground works - Albert Street 

January 2026 - March 2026

Road reconstruction and footpaths 

February 2026 - July 2026

Finishing touches - line-marking, signage, tree planting 

July 2026 - October 2026

Expected Project Completion 

October 2026


*These dates are subject to weather and ground conditions.